SuperCalX

Gantt Chart vs PERT Chart vs Timeline: Which to Use

By Dr. Ahmed Mortuza Saleque · Updated · How we check our content

The short answer

A Gantt chart is a bar chart of tasks against a calendar, so it shows when each task happens and how long it takes. A PERT chart is a network of boxes and arrows that shows which tasks depend on which, and helps find the critical path. A timeline only shows key dates. Use PERT to plan the logic, then a Gantt chart to schedule and communicate it.

Open the Gantt Chart Maker →
Side-by-side comparison of a Gantt chart with bars on a calendar and a PERT chart with task boxes connected by arrows, showing the critical path
Tap the image to enlarge it. Free to share with a link to this page.

Side by side

Gantt chartPERT chartTimeline
ShapeBars on a calendarBoxes joined by arrowsPoints on a line
Best atWhen and how longOrder and dependenciesKey dates at a glance
Shows durationsYes, bar lengthAs numbers in boxesRarely
Shows dependenciesOptional arrowsYes, the whole pointNo
Critical pathCan be highlightedFound directlyNo
Easy for funders and clientsYesLess soYes

Worked example: five tasks

A small study, with durations in weeks and what each task must wait for.

TaskWeeksDepends on
A. Design survey2–
B. Ethics approval4A
C. Recruit participants3A
D. Collect data5B and C
E. Analyse and report3D

Finding the critical path

  1. Path A → B → D → E takes 2 + 4 + 5 + 3 = 14 weeks.
  2. Path A → C → D → E takes 2 + 3 + 5 + 3 = 13 weeks.
  3. The longest path, A → B → D → E, is the critical path: the project cannot finish in under 14 weeks.
  4. Task C has 1 week of slack. It can start a week late without delaying the end.

A PERT chart makes this logic visible. A Gantt chart then places the same tasks on a calendar: in the Gantt Chart Maker you can link each task to the one it waits for and show the arrows.

Three-point estimates in PERT

PERT originally estimated each task with three numbers: optimistic (O), most likely (M) and pessimistic (P). The expected time is (O + 4M + P) ÷ 6. Ethics approval with O = 3, M = 4 and P = 8 weeks gives (3 + 16 + 8) ÷ 6 = 4.5 weeks. The method puts weight on the most likely value while still accounting for a long tail.

And Kanban or a roadmap?

  • Kanban board: columns of cards (to do, doing, done). Good for ongoing work without fixed dates; no time axis.
  • Roadmap: a high-level Gantt chart of themes or releases by quarter, with little task detail. The Roadmap style in the Gantt Chart Maker gives this look.

Common questions

Is a PERT chart better than a Gantt chart?

Neither is better; they answer different questions. PERT shows dependencies and the critical path, Gantt shows the schedule. Many projects use both.

What does PERT stand for?

Program Evaluation and Review Technique, developed for the U.S. Navy Polaris missile programme in the late 1950s.

Can a Gantt chart show dependencies?

Yes. Arrows from the end of one bar to the start of another show that a task waits for another.

What is the difference between a Gantt chart and a timeline?

A timeline marks dates and events on a single line. A Gantt chart gives each task its own row and a bar showing how long it lasts.

Calculators for this article

More from the blog